But we had like 90 days to basically build this incredible infrastructure. The cooling systems we bought, they had never been used anywhere. So, and you never wanna do that on a high-risk project. So we had that. The computers were right. out of the box [laughing] and had never been, you know, used anywhere on any major project. The communications fabric that was needed to tie this together, none of the current communications fabrics would support the system on the scale we wanted. So we had to go with an Israeli company and they had never done anything on this scale. So we had this critical project that we needed to be up and running and testing in order to be part of this international competition by August. And we had all these elements, but they all came through. And so it was an incredibly fun project.